6 steps to learn to plant rebar

Positioning
According to the requirements of the design drawings for the line positioning, drilling position, model in the required reinforcement at the place to make a clear mark, in order to drill holes.

Positioning should be as far as possible to avoid the original structure of the steel bar position and stress concentration site,

if the hole bit encountered on the substrate has a steel bar, drilling position can be adjusted appropriately.

However, it should be planted on the inside of the hoop (to the beam, column) or the inner side of the distribution bar (to the plate, shear wall),

and the hole can be as close as possible to the long existing steel bar (the force transfer effect is better).

Drilling
Use an electric hammer to drill holes, in case of steel bars should adjust the hole position to avoid.

Drilling aperture 4∽8mm (small diameter steel bar to take low value, large diameter  steel bar to take high value).

If the concrete strength grade is not less than C20,ⅱ class (Ⅲ grade) grade  rebar,  Q235, Q345 class bolts and 5.6 stage screw,  drilling hole depth 15d, 

single drawing test anchorage force is generally greater than the steel yield force value. Round steel or screw, drilling depth should be increased by  more than 5d.


(after systematic test, it is shown that the small diameter round steel  reinforcement,  the end should adopt the Bending hook style, the Anchorage comprehensive  performance is the best), at this time the drilling aperture should be larger  than the end size 1–2mm.


If the concrete strength level is lower than C20, or the reinforcement on the vegetarian concrete (or rock), the anchorage depth should be increased.
When the actual Anchorage force required is small (such as bolt fixing  apparatus,  pipeline, bracket, etc.), the drilling depth can be determined according to  the length of the bolt, but the depth should not be less than 5d.


Drilling effective depth from the component surface solid concrete  calculation.Drilling  generally should be vertical concrete member plane, the tilt is not greater  than 8°  (except for special requirements).

Clear Hole
Clear Hole If the hole is not done in place, the residue of dust, oil and water will reduce the bonding strength of the reinforced adhesive, thus directly  affecting the quality of  the anchorage. Therefore, the treatment of clear hole must be completely  effective.


After drilling, apply brush to the dust of the hole wall and loose particles on the hole  wall, and then use compressed air or cylinder to blow out the ash in the  hole, repeated 3∽5 times, until the hole thoroughly clean.


Hole should be guaranteed to dry, if there is oil need cotton yarn dipped in  acetone will wipe inside the hole clean. If not immediately after the hole is planted, the cotton wire is used to close the orifice to prevent dust and  debris from entering the hole.

Steel Bar Treatment
Steel Bar Treatment For the implanted steel surface treatment, there is oil  should be  cleaned first, can be used cleaning agent to brush clean water, dry moisture.


There is rust to take sandpaper or wire brush polishing rust removal, the  use of cotton cloth dipped in acetone or alcohol will be implanted in the  length of the screw, steel  surface wipe clean before you can use.

Adhesive Injection
XQ modified Epoxy injection reinforced adhesive with special rubber gun,  no need for  artificial glue. Install the static mixer in the rubber bottle, with a small  amount of glue  gun to squeeze off the front end of the part is not mixed uniform glue  (about 40 cm),  and then injection in the hole glue;

should be guaranteed by the hole bottom to the orifice of the injection order, as far as possible do not mix bubbles, glue injection full hole 2/3 can, glue  too little affect the  adhesion, too much is unnecessary waste, After the steel bar is plugged into the  bottom of the hole, excess glue should overflow from the hole.

Curing 
Curing Generally at room temperature (25 ℃), XQ injection reinforced  adhesive  static maintenance 12 hours after the pull-up inspection requirements can be reached. 

During colloidal curing, the planted steel bar shall not be disturbed to  avoid vibration.  The following is the curing schedule of different ambient temperatures of  xq injection  reinforced adhesive, which can be used for reference.